Honey Mesquite Wind Farm
ERCOT-26INR0447BetaActiveWindERCOTLBNL + Live
180.48 MW generation in Glasscock, TX · In queue since March 2024 · Proposed COD December 2026
180.48 MW
Capacity
1
Components
Wind
2y 1m
In Queue
IA Executed
IA Status
Signed Sep 2024
Interconnection Timeline
Queue → IA
6 months
IA → COD
2y 3m
Total Duration
6 months
Construction75%
Queue EntryMar 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementSep 16, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-12-15
Project Details
State
TX
County
Glasscock
Region
ERCOT
Developer
Honey Mesquite Wind Farm , LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59902 Sand Bluff 345kV
Data Source
LBNL + Live