Hamby Solar
ERCOT-26INR0440BetaActiveSolarERCOTLBNL + Live
71.4 MW generation in Jones, TX · In queue since March 2024 · Proposed COD June 2028
71.4 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 3m
Facilities Study50%
Queue EntryMar 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-27
Project Details
State
TX
County
Jones
Region
ERCOT
Developer
Abilene GCE LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6245 ABILENE ROBERTSON PRISON 69 KV
Data Source
LBNL + Live
No news available for this project.