Twinwood Solar 1
BetaActiveSolarERCOTLBNL + Live
358.06 MW generation in Waller, TX · In queue since March 2024 · Proposed COD October 2027
358.06 MW
Capacity
1
Components
Solar
2 years
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 7m
Facilities Study50%
Queue EntryMar 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-27
Project Details
State
TX
County
Waller
Region
ERCOT
Developer
Twinwood PV1, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 44750 FULSHR_S25_8 - 44860 TWINWD_S25_8
Data Source
LBNL + Live