TE Smith Storage 2
BetaActiveBatteryERCOTLBNL + Live
125.36 MW storage in Rockwall, TX · In queue since April 2024 · Proposed COD August 2027
125.36 MW
Capacity
1
Components
Battery
1y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 4m
Facilities Study50%
Queue EntryApr 15, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-16
Project Details
State
TX
County
Rockwall
Region
ERCOT
Developer
Smith II Battery Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
2483 Royse 345kV
Data Source
LBNL + Live