GAMAY ENERGY STORAGE
ERCOT-26INR0417BetaActiveBatteryERCOTLBNL + Live
418.6 MW storage in Brazoria, TX · In queue since February 2024 · Proposed COD March 2027
418.6 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 1m
Facilities Study50%
Queue EntryFeb 7, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-01
Project Details
State
TX
County
Brazoria
Region
ERCOT
Developer
GAMAY ENERGY STORAGE LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV Line from TNFM524 (39703) to West Columbia Main (39500), in Brazoria County.
Data Source
LBNL + Live
No news available for this project.