BumbleBee Solar
BetaActiveSolarERCOTLBNL + Live
211.6 MW generation in Bee, TX · In queue since February 2024 · Proposed COD July 2027
211.6 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 5m
Facilities Study50%
Queue EntryFeb 27, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
TX
County
Bee
Region
ERCOT
Developer
BumbleBee Solar Farm LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 5725 PawneeSW5 - 8689 Tango
Data Source
LBNL + Live
No news available for this project.