Lucky 7 Solar
ERCOT-26INR0409BetaActiveSolarERCOTLBNL + Live
100.8 MW generation in Hopkins, TX · In queue since March 2024 · Proposed COD September 2027
100.8 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 6m
Facilities Study50%
Queue EntryMar 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-20
Project Details
State
TX
County
Hopkins
Region
ERCOT
Developer
OCI SOLAR POWER LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1697 SULPHUR SPRINGS SWITCH - 2464 CASH SWITCH
Data Source
LBNL + Live
News & Articles (1)Beta
Last updated 2026-03-26