Aggie Solar Project SLF
BetaActiveSolarERCOTLBNL + Live
103.7 MW generation in Reeves, TX · In queue since February 2024 · Proposed COD June 2027
103.7 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 4m
Facilities Study50%
Queue EntryFeb 2, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
TX
County
Reeves
Region
ERCOT
Developer
reNRG TX 8 LLC
Utility
—
Entity
ERCOT
Point of Interconnection
POI: COYOTE SPRINGS SUBSTATION - 138KV BUS NUMBER : 38113 COUNTY : REEVES POI LOCATION: 31.396675, -103.6252777
Data Source
LBNL + Live
No news available for this project.