Larimar Solar — Project Summary

Queue ID
ERCOT-26INR0378
Capacity
150.91 MW
Technology
Solar
Status
active
Location
Bee, TX
Region
ERCOT
Developer
BT S7 Solar, LLC
IA Status
Facility Study

Larimar Solar

BetaActiveSolarERCOTLBNL

150.91 MW generation in Bee, TX · In queue since January 2024 · Proposed COD December 2026

150.91 MW

Capacity

1

Components

Solar

2y 2m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 11m

Facilities Study50%
Queue EntryJan 11, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-18

Project Details

State

TX

County

Bee

Region

ERCOT

Developer

BT S7 Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138 kV 8186 KENEDYSW4A _x0010_ 8590 TULETA4A

Data Source

LBNL

No news available for this project.