Centennial Solar — Project Summary

Queue ID
ERCOT-26INR0372
Capacity
61.36 MW
Technology
Solar
Status
active
Location
Menard, TX
Region
ERCOT
Developer
Centennial AD 8 LLC
IA Status
Facility Study

Centennial Solar

BetaActiveSolarERCOTLBNL

61.36 MW generation in Menard, TX · In queue since January 2024 · Proposed COD April 2028

61.36 MW

Capacity

1

Components

Solar

2y 2m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 3m

Facilities Study50%
Queue EntryJan 3, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-29

Project Details

State

TX

County

Menard

Region

ERCOT

Developer

Centennial AD 8 LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 6364 YELLOW JACKET - 76390 FORT MASON

Data Source

LBNL

No news available for this project.