Pollo Pinto Solar
BetaActiveSolarERCOTLBNL + Live
150.8 MW generation in Palo Pinto, TX · In queue since February 2024 · Proposed COD August 2027
150.8 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 6m
Facilities Study50%
Queue EntryFeb 27, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-15
Project Details
State
TX
County
Palo Pinto
Region
ERCOT
Developer
TX Palo Pinto SB 6, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 331 RWMILLER - 320 JAYBIRD
Data Source
LBNL + Live
No news available for this project.