Pollo Pinto Solar — Project Summary

Queue ID
ERCOT-26INR0364
Capacity
150.8 MW
Technology
Solar
Status
active
Location
Palo Pinto, TX
Region
ERCOT
Developer
TX Palo Pinto SB 6, LLC
IA Status
Facility Study

Pollo Pinto Solar

BetaActiveSolarERCOTLBNL + Live

150.8 MW generation in Palo Pinto, TX · In queue since February 2024 · Proposed COD August 2027

150.8 MW

Capacity

1

Components

Solar

2y 1m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 6m

Facilities Study50%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-08-15

Project Details

State

TX

County

Palo Pinto

Region

ERCOT

Developer

TX Palo Pinto SB 6, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 331 RWMILLER - 320 JAYBIRD

Data Source

LBNL + Live

No news available for this project.