Jack County III _x0013_ 345 kV (TEF -Due Diligence)
BetaActiveGasERCOTLBNL + Live
660 MW generation in Jack, TX · In queue since November 2023 · Proposed COD July 2027
660 MW
Capacity
1
Components
Gas
2y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 8m
Facilities Study50%
Queue EntryNov 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
TX
County
Jack
Region
ERCOT
Developer
Jack County Power Development, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Substation Name: JACK COUNTY 2 PLANT STATION CODE: JCKCNTY2 BUS NUMBER: 575
Data Source
LBNL + Live
No news available for this project.