Jack County III _x0013_ 138 kV
BetaActiveGasERCOTLBNL
660 MW generation in Jack, TX · In queue since November 2023 · Proposed COD May 2026
660 MW
Capacity
1
Components
Gas
2y 4m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 6m
Facilities Study50%
Queue EntryNov 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-05-01
Project Details
State
TX
County
Jack
Region
ERCOT
Developer
Jack County Power Development, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
579 JACK COUNTY 138kV
Data Source
LBNL
No news available for this project.