Midfield PV Project SLF
BetaActiveSolarERCOTLBNL + Live
150 MW generation in Matagorda, TX · In queue since December 2023 · Proposed COD July 2028
150 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 7m
Facilities Study50%
Queue EntryDec 4, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
TX
County
Matagorda
Region
ERCOT
Developer
HQC Solar Holdings 1, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 8121 Blessing - 8125 Lolita
Data Source
LBNL + Live
No news available for this project.