NET Power Demonstration plant
BetaActiveGasERCOTLBNL + Live
25.5 MW generation in Harris, TX · In queue since December 2023 · Proposed COD August 2027
25.5 MW
Capacity
1
Components
Gas
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 8m
Facilities Study50%
Queue EntryDec 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-21
Project Details
State
TX
County
Harris
Region
ERCOT
Developer
NET Power LLC
Utility
—
Entity
ERCOT
Point of Interconnection
42360 Mirage POI 8 138kV
Data Source
LBNL + Live
No news available for this project.