TOCE TX BESS 2 — Project Summary

Queue ID
ERCOT-26INR0334
Capacity
523.38 MW
Technology
Battery
Status
active
Location
Wharton, TX
Region
ERCOT
Developer
TOCE TX BESS 2, LLC
IA Status
Facility Study

TOCE TX BESS 2

BetaActiveBatteryERCOTLBNL

523.38 MW storage in Wharton, TX · In queue since February 2024 · Proposed COD August 2027

523.38 MW

Capacity

1

Components

Battery

2y 1m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 6m

Facilities Study50%
Queue EntryFeb 2, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-08-01

Project Details

State

TX

County

Wharton

Region

ERCOT

Developer

TOCE TX BESS 2, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 44200 Hillje - 44000 WA Parrish 345 kV

Data Source

LBNL

No news available for this project.