Leaning Tree BESS — Project Summary

Queue ID
ERCOT-26INR0326
Capacity
256.1 MW
Technology
Battery
Status
active
Location
Throckmorton, TX
Region
ERCOT
Developer
RamZ BESS, LLC
IA Status
Facility Study

Leaning Tree BESS

BetaActiveBatteryERCOTLBNL

256.1 MW storage in Throckmorton, TX · In queue since November 2023 · Proposed COD February 2027

256.1 MW

Capacity

1

Components

Battery

2y 4m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 3m

Facilities Study50%
Queue EntryNov 30, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-02-13

Project Details

State

TX

County

Throckmorton

Region

ERCOT

Developer

RamZ BESS, LLC

Utility

Entity

ERCOT

Point of Interconnection

To Tap 345 kV Thomas Price Switch (Bus# 11523) to Clear Crossing (Bus# 60515) Line

Data Source

LBNL

No news available for this project.