Augite Storage
BetaActiveBatteryERCOTLBNL
151.41 MW storage in Starr, TX · In queue since February 2024 · Proposed COD December 2027
151.41 MW
Capacity
1
Components
Battery
2y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 10m
Facilities Study50%
Queue EntryFeb 2, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-30
Project Details
State
TX
County
Starr
Region
ERCOT
Developer
BT Augite Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 8798 La Grulla - 8355 Goodwin
Data Source
LBNL