Sandford Solar
BetaActiveSolarERCOTLBNL + Live
126.18 MW generation in Wise, TX · In queue since January 2024 · Proposed COD August 2028
126.18 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 7m
Facilities Study50%
Queue EntryJan 3, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-15
Project Details
State
TX
County
Wise
Region
ERCOT
Developer
BT Sandford Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV Bird Dog (Bus #11736) - Jacksboro (Bus #1429)
Data Source
LBNL + Live
No news available for this project.