Bhalu Storage
BetaActiveBatteryERCOTLBNL + Live
205.5 MW storage in Howard, TX · In queue since October 2023 · Proposed COD April 2028
205.5 MW
Capacity
1
Components
Battery
2y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 6m
Facilities Study50%
Queue EntryOct 30, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-21
Project Details
State
TX
County
Howard
Region
ERCOT
Developer
Bhalu Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV Bulldog (#23833) _x0013_ Elbow (#23834)
Data Source
LBNL + Live
No news available for this project.