Longleaf Power Station (TEF-Due Diligence) — Project Summary

Queue ID
ERCOT-26INR0294
Capacity
600 MW
Technology
Gas
Status
active
Location
Angelina, TX
Region
ERCOT
Developer
WattBridge Texas Holding, LLC
IA Status
Facility Study

Longleaf Power Station (TEF-Due Diligence)

BetaActiveGasERCOTLBNL + Live

600 MW generation in Angelina, TX · In queue since October 2023 · Proposed COD March 2029

600 MW

Capacity

1

Components

Gas

2y 5m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 5m

Facilities Study50%
Queue EntryOct 13, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-31

Project Details

State

TX

County

Angelina

Region

ERCOT

Developer

WattBridge Texas Holding, LLC

Utility

Entity

ERCOT

Point of Interconnection

Redland Substation (# 3321)

Data Source

LBNL + Live

No news available for this project.