Bonaparte BESS — Project Summary

Queue ID
ERCOT-26INR0283
Capacity
153.67 MW
Technology
Battery
Status
active
Location
Lee, TX
Region
ERCOT
Developer
Bonaparte BESS, LLC
IA Status
Facility Study

Bonaparte BESS

BetaActiveBatteryERCOTLBNL

153.67 MW storage in Lee, TX · In queue since November 2023 · Proposed COD August 2026

153.67 MW

Capacity

1

Components

Battery

2y 4m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 9m

Facilities Study50%
Queue EntryNov 14, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-08-01

Project Details

State

TX

County

Lee

Region

ERCOT

Developer

Bonaparte BESS, LLC

Utility

Entity

ERCOT

Point of Interconnection

7568 Lincoln 138 kV

Data Source

LBNL

No news available for this project.