Pethrus BESS
BetaActiveBatteryERCOTLBNL + Live
174.08 MW storage in Wichita, TX · In queue since September 2023 · Proposed COD July 2028
174.08 MW
Capacity
1
Components
Battery
2y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 10m
Facilities Study50%
Queue EntrySep 23, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-25
Project Details
State
TX
County
Wichita
Region
ERCOT
Developer
Pethrus BESS, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap Wichita Falls Switch (#1464) _x0013_ North Star (#1467) 138 kV Line
Data Source
LBNL + Live
No news available for this project.