Moccasin Solar
806.8 MW generation in Stonewall, TX · In queue since September 2023 · Proposed COD July 2027
806.8 MW
Capacity
1
Components
Solar
2y 7m
In Queue
IA Executed
IA Status
Signed Sep 2024
Queue → IA
1 year
IA → COD
2y 10m
Total Duration
1 year
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-07-06
State
TX
County
Stonewall
Region
ERCOT
Developer
Swenson Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tapping the 345 kV Line from Kirchhoff (Bus# 60707) to Clear Crossing (Bus# 60515)
Data Source
LBNL + Live