Operation Sunshine
ERCOT-26INR0255BetaActiveSolarERCOTLBNL + Live
602.1 MW generation in Concho, TX · In queue since November 2023 · Proposed COD March 2028
602.1 MW
Capacity
1
Components
Solar
2y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 4m
Facilities Study50%
Queue EntryNov 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-12
Project Details
State
TX
County
Concho
Region
ERCOT
Developer
Duck Creek Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7077 Amos Creek 345kV
Data Source
LBNL + Live
No news available for this project.