Goldfinch Storage — Project Summary

Queue ID
ERCOT-26INR0254
Capacity
100.44 MW
Technology
Battery
Status
active
Location
Van Zandt, TX
Region
ERCOT
Developer
BT DJ4M Solar, LLC
IA Status
Facility Study

Goldfinch Storage

BetaActiveBatteryERCOTLBNL + Live

100.44 MW storage in Van Zandt, TX · In queue since October 2023 · Proposed COD March 2028

100.44 MW

Capacity

1

Components

Battery

2y 5m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 5m

Facilities Study50%
Queue EntryOct 4, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-18

Project Details

State

TX

County

Van Zandt

Region

ERCOT

Developer

BT DJ4M Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap Connection Bus 2485 Poetry Switch _x0013_ 3223 Shamburger Switch

Data Source

LBNL + Live