Neutron Storage
ERCOT-26INR0252BetaActiveBatteryERCOTLBNL + Live
104.36 MW storage in Mclennan, TX · In queue since September 2023 · Proposed COD April 2028
104.36 MW
Capacity
1
Components
Battery
2y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 7m
Facilities Study50%
Queue EntrySep 8, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-29
Project Details
State
TX
County
Mclennan
Region
ERCOT
Developer
Neutron Storage
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 13405 Trading House - 68090 Sam Switch
Data Source
LBNL + Live
No news available for this project.