Sengun BESS
BetaActiveBatteryERCOTLBNL + Live
200.89 MW storage in Nueces, TX · In queue since January 2024 · Proposed COD March 2028
200.89 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 2m
Facilities Study50%
Queue EntryJan 3, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-17
Project Details
State
TX
County
Nueces
Region
ERCOT
Developer
BRP Blue Topaz 12, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
WEST_OSO4A (8484) 138 KV
Data Source
LBNL + Live
No news available for this project.