Jane Storage Energy Center
BetaActiveBatteryERCOTLBNL + Live
240.6 MW storage in Martin, TX · In queue since September 2023 · Proposed COD March 2027
240.6 MW
Capacity
1
Components
Battery
2y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 6m
Facilities Study50%
Queue EntrySep 8, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-01
Project Details
State
TX
County
Martin
Region
ERCOT
Developer
NMRE Holdings, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
59901 Grelton 345 kV
Data Source
LBNL + Live