Noor Solar
BetaActiveSolarERCOTLBNL
188.2 MW generation in Liberty, TX · In queue since October 2023 · Proposed COD March 2028
188.2 MW
Capacity
1
Components
Solar
2y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 5m
Facilities Study50%
Queue EntryOct 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
TX
County
Liberty
Region
ERCOT
Developer
Industrial Kilo Project LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 40390 Crosby - 40680 Placid Ckt 86
Data Source
LBNL
No news available for this project.