Energy City BESS
BetaActiveBatteryERCOTLBNL + Live
204.9 MW storage in Midland, TX · In queue since October 2023 · Proposed COD June 2027
204.9 MW
Capacity
1
Components
Battery
2y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 8m
Facilities Study50%
Queue EntryOct 4, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
TX
County
Midland
Region
ERCOT
Developer
Energy City BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 1179 Texaco Mabee Tap - 1200 Mariensfield
Data Source
LBNL + Live
No news available for this project.