Energy City BESS — Project Summary

Queue ID
ERCOT-26INR0231
Capacity
204.9 MW
Technology
Battery
Status
active
Location
Midland, TX
Region
ERCOT
Developer
Energy City BESS LLC
IA Status
Facility Study

Energy City BESS

BetaActiveBatteryERCOTLBNL + Live

204.9 MW storage in Midland, TX · In queue since October 2023 · Proposed COD June 2027

204.9 MW

Capacity

1

Components

Battery

2y 5m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 8m

Facilities Study50%
Queue EntryOct 4, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-30

Project Details

State

TX

County

Midland

Region

ERCOT

Developer

Energy City BESS LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 1179 Texaco Mabee Tap - 1200 Mariensfield

Data Source

LBNL + Live

No news available for this project.