Pamplona Solar — Project Summary

Queue ID
ERCOT-26INR0229
Capacity
42.38 MW
Technology
Solar
Status
active
Location
Austin, TX
Region
ERCOT
Developer
Karol Solar III
IA Status
Facility Study

Pamplona Solar

BetaActiveSolarERCOTLBNL + Live

42.38 MW generation in Austin, TX · In queue since August 2023 · Proposed COD October 2028

42.38 MW

Capacity

1

Components

Solar

2y 7m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 2m

Facilities Study50%
Queue EntryAug 14, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-17

Project Details

State

TX

County

Austin

Region

ERCOT

Developer

Karol Solar III

Utility

Entity

ERCOT

Point of Interconnection

Tap 138 kV 44740 WALLIS_S65_8 - 44700 GEBHRT_X65B8 Ckt#65

Data Source

LBNL + Live

No news available for this project.