Pamplona Solar
BetaActiveSolarERCOTLBNL + Live
42.38 MW generation in Austin, TX · In queue since August 2023 · Proposed COD October 2028
42.38 MW
Capacity
1
Components
Solar
2y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 2m
Facilities Study50%
Queue EntryAug 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-17
Project Details
State
TX
County
Austin
Region
ERCOT
Developer
Karol Solar III
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 44740 WALLIS_S65_8 - 44700 GEBHRT_X65B8 Ckt#65
Data Source
LBNL + Live
No news available for this project.