Santa Monica Solar
BetaActiveSolarERCOTLBNL + Live
105.85 MW generation in Navarro, TX · In queue since September 2023 · Proposed COD September 2028
105.85 MW
Capacity
1
Components
Solar
2y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5 years
Facilities Study50%
Queue EntrySep 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-20
Project Details
State
TX
County
Navarro
Region
ERCOT
Developer
Karol Solar IV
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 KV 68091 NAVARRO - 3381 BIGBRNW_5 Ckt 2
Data Source
LBNL + Live
No news available for this project.