GOTHAM BESS — Project Summary

Queue ID
ERCOT-26INR0222
Capacity
151.2 MW
Technology
Battery
Status
active
Location
Nueces, TX
Region
ERCOT
Developer
AEU BATTERY PROJECT IV LLC
IA Status
Facility Study

GOTHAM BESS

BetaActiveBatteryERCOTLBNL + Live

151.2 MW storage in Nueces, TX · In queue since July 2023 · Proposed COD March 2027

151.2 MW

Capacity

1

Components

Battery

2y 8m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 8m

Facilities Study50%
Queue EntryJul 31, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-17

Project Details

State

TX

County

Nueces

Region

ERCOT

Developer

AEU BATTERY PROJECT IV LLC

Utility

Entity

ERCOT

Point of Interconnection

5640 DRISCOLLSUB9 69kV

Data Source

LBNL + Live