NEZUKO BESS
BetaActiveBatteryERCOTLBNL
63.14 MW storage in Shackelford, TX · In queue since July 2023 · Proposed COD January 2028
63.14 MW
Capacity
1
Components
Battery
2y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 6m
Facilities Study50%
Queue EntryJul 31, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-24
Project Details
State
TX
County
Shackelford
Region
ERCOT
Developer
AEU BATTERY PROJECT I LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 69 kV 6202 ALBNY_FD2A - 60426 HULLTOWN2A
Data Source
LBNL
No news available for this project.