Vaughn Energy Storage — Project Summary

Queue ID
ERCOT-26INR0200
Capacity
200.6 MW
Technology
Battery
Status
active
Location
Grimes, TX
Region
ERCOT
Developer
Vaughn Battery Storage, LLC
IA Status
Facility Study

Vaughn Energy Storage

BetaActiveBatteryERCOTLBNL + Live

200.6 MW storage in Grimes, TX · In queue since August 2023 · Proposed COD December 2027

200.6 MW

Capacity

1

Components

Battery

2y 7m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 4m

Facilities Study50%
Queue EntryAug 21, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

TX

County

Grimes

Region

ERCOT

Developer

Vaughn Battery Storage, LLC

Utility

Entity

ERCOT

Point of Interconnection

13 Keith 138kV

Data Source

LBNL + Live