TRIFECTA Gas
453 MW generation in Midland, TX · In queue since June 2023 · Proposed COD February 2030
453 MW
Capacity
1
Components
Gas
2y 9m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-02-11
State
TX
County
Midland
Region
ERCOT
Developer
NET Power
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 1185 Midland County Northwest Switch (bus #1185) _x0013_ Midland East (bus #1021) 345 kV Line Ckt 01
Data Source
LBNL + Live
Earnings call transcript: NET Power Q3 2025 reveals strategic pivot
NET Power Inc. (NPWR) reported its third-quarter earnings for 2025, revealing a significant earnings per share (EPS) loss of $5.28,...
Texas regulators approve 2 Entergy gas plants with $2.4B ‘hard cap’
The new resources are necessary, said PUCT Chair Thomas Gleeson, “but we also have the mandate to protect customers, and I think this...
Texas regulators approve 2 Entergy gas plants with $2.4B ‘hard cap’
The new resources are necessary, said PUCT Chair Thomas Gleeson, “but we also have the mandate to protect customers, and I think this...
Texas regulators approve 2 Entergy gas plants with $2.4B ‘hard cap’
The new resources are necessary, said PUCT Chair Thomas Gleeson, “but we also have the mandate to protect customers, and I think this...
Last updated 2026-03-26