TRIFECTA Gas — Project Summary

Queue ID
ERCOT-26INR0183
Capacity
453 MW
Technology
Gas
Status
active
Location
Midland, TX
Region
ERCOT
Developer
NET Power
IA Status
Facility Study

TRIFECTA Gas

BetaActiveGasERCOTLBNL + Live

453 MW generation in Midland, TX · In queue since June 2023 · Proposed COD February 2030

453 MW

Capacity

1

Components

Gas

2y 9m

In Queue

Facility Study

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

6y 8m

Facilities Study50%
Queue EntryJun 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-02-11

Project Details

State

TX

County

Midland

Region

ERCOT

Developer

NET Power

Utility

Entity

ERCOT

Point of Interconnection

Tap 345 kV 1185 Midland County Northwest Switch (bus #1185) _x0013_ Midland East (bus #1021) 345 kV Line Ckt 01

Data Source

LBNL + Live