Alliance Solar
BetaActiveSolarERCOTLBNL
175 MW generation in Navarro, TX · In queue since July 2023 · Proposed COD July 2028
175 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5 years
Facilities Study50%
Queue EntryJul 10, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
TX
County
Navarro
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 68091 Navarro - 1907 Venus Switch
Data Source
LBNL
No news available for this project.