Timberline Solar
201 MW generation in Nacogdoches, TX · In queue since August 2023 · Proposed COD April 2029
201 MW
Capacity
1
Components
Solar
2y 7m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-20
State
TX
County
Nacogdoches
Region
ERCOT
Developer
Timberline Renewables, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 3119 Nacogdoches SE - 3116 Mt Enterprise
Data Source
LBNL + Live
BC Exteriors LLC Highlights GAF Solar Shingles in Michigan
FENTON, MI – March 23, 2026 – PRESSADVANTAGE –. BC Exteriors LLC, a GAF Master Elite Roofing Contractor, offers the GAF Energy Timberline Solar Roofing...
GAF Energy's $100M factory in Georgetown already reaping dividends for solar shingle maker
GAF Energy has wrapped up construction on its massive Georgetown project. The company plans to be at full operations by the end of the year.
GAF Energy's $100M factory in Georgetown already reaping dividends for solar shingle maker
GAF Energy has wrapped up construction on its massive Georgetown project. The company plans to be at full operations by the end of the year.
Sound of GAF Energy's $100M factory operating north of Austin like 'music,' exec says
GAF Energy has wrapped up construction on its massive Georgetown project. The company plans to be at full operations by the end of the year.
Last updated 2026-03-26