Ross Storage
510.99 MW storage in Refugio, TX · In queue since August 2023 · Proposed COD July 2027
510.99 MW
Capacity
1
Components
Battery
2y 8m
In Queue
IA Executed
IA Status
Signed Jun 2024
Queue → IA
10 months
IA → COD
3y 1m
Total Duration
10 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-07-31
State
TX
County
Refugio
Region
ERCOT
Developer
S&S Renewables, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap the 345 kV Angstrom (#8249) _x0013_ Static (#8676) line; AEP
Data Source
LBNL + Live