Ross Solar
ERCOT-26INR0155BetaActiveSolarERCOTLBNL + Live
1,025.57 MW generation in Refugio, TX · In queue since July 2023 · Proposed COD July 2027
1,025.57 MW
Capacity
1
Components
Solar
2y 9m
In Queue
IA Executed
IA Status
Signed Jun 2024
Interconnection Timeline
Queue → IA
11 months
IA → COD
3y 1m
Total Duration
11 months
Construction75%
Queue EntryJul 31, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJun 27, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-07-31
Project Details
State
TX
County
Refugio
Region
ERCOT
Developer
S&S Renewables, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 8249 Angstrom _x0013_ 8676 Static
Data Source
LBNL + Live