Proving Ground Solar — Project Summary

Queue ID
ERCOT-26INR0150
Capacity
82.1 MW
Technology
Solar
Status
active
Location
Schleicher, TX
Region
ERCOT
Developer
Lantana Solar LLC
IA Status
Facility Study

Proving Ground Solar

BetaActiveSolarERCOTLBNL + Live

82.1 MW generation in Schleicher, TX · In queue since July 2023 · Proposed COD June 2028

82.1 MW

Capacity

1

Components

Solar

2y 8m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 11m

Facilities Study50%
Queue EntryJul 10, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-30

Project Details

State

TX

County

Schleicher

Region

ERCOT

Developer

Lantana Solar LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138 kV Live Oak (6500) - Santiago (6490)

Data Source

LBNL + Live

No news available for this project.