Proving Ground Solar
BetaActiveSolarERCOTLBNL + Live
82.1 MW generation in Schleicher, TX · In queue since July 2023 · Proposed COD June 2028
82.1 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 11m
Facilities Study50%
Queue EntryJul 10, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
TX
County
Schleicher
Region
ERCOT
Developer
Lantana Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV Live Oak (6500) - Santiago (6490)
Data Source
LBNL + Live
No news available for this project.