Seven Springs Solar
ERCOT-26INR0147BetaActiveSolarERCOTLBNL + Live
145.57 MW generation in Coryell, TX · In queue since September 2023 · Proposed COD May 2028
145.57 MW
Capacity
1
Components
Solar
2y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 8m
Facilities Study50%
Queue EntrySep 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-26
Project Details
State
TX
County
Coryell
Region
ERCOT
Developer
Hancock Springs, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 7061 COPPERAS COVE 7260 Kempner 138kV
Data Source
LBNL + Live
No news available for this project.