DMF Sagerton Solar SLF — Project Summary

Queue ID
ERCOT-26INR0146
Capacity
125.5 MW
Technology
Solar
Status
active
Location
Haskell, TX
Region
ERCOT
Developer
Double Mountain Fork LLC
IA Status
Facility Study

DMF Sagerton Solar SLF

BetaActiveSolarERCOTLBNL + Live

125.5 MW generation in Haskell, TX · In queue since July 2023 · Proposed COD December 2028

125.5 MW

Capacity

1

Components

Solar

2y 8m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 5m

Facilities Study50%
Queue EntryJul 31, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-15

Project Details

State

TX

County

Haskell

Region

ERCOT

Developer

Double Mountain Fork LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 6158 Aspermont _x0013_ 6161 Paint Creek

Data Source

LBNL + Live

No news available for this project.