Myers Storage
BetaActiveBatteryERCOTLBNL + Live
75.7 MW storage in Bee, TX · In queue since June 2023 · Proposed COD May 2028
75.7 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 11m
Facilities Study50%
Queue EntryJun 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-22
Project Details
State
TX
County
Bee
Region
ERCOT
Developer
BT Myers Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
8629 Baez 69 kV
Data Source
LBNL + Live