SunWave Solar
BetaActiveSolarERCOTLBNL
159.89 MW generation in Nueces, TX · In queue since May 2023 · Proposed COD June 2028
159.89 MW
Capacity
1
Components
Solar
2y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 1m
Facilities Study50%
Queue EntryMay 26, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
TX
County
Nueces
Region
ERCOT
Developer
Buckeye Nueces Bay Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
8459 Bunsen 138kV
Data Source
LBNL