Falcon Zapata Storage 138 — Project Summary

Queue ID
ERCOT-26INR0116
Capacity
200.79 MW
Technology
Battery
Status
active
Location
Zapata, TX
Region
ERCOT
Developer
Falcon BESS, LLC
IA Status
Facility Study

Falcon Zapata Storage 138

ERCOT-26INR0116BetaActiveBatteryERCOTLBNL + Live

200.79 MW storage in Zapata, TX · In queue since May 2023 · Proposed COD March 2028

200.79 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 10m

Facilities Study50%
Queue EntryMay 15, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-11

Project Details

State

TX

County

Zapata

Region

ERCOT

Developer

Falcon BESS, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 8299 Zapata - 8957 Lopeno

Data Source

LBNL + Live