Meitner Wind
ERCOT-26INR0113BetaActiveWindERCOTLBNL + Live
836.5 MW generation in Gray, TX · In queue since July 2023 · Proposed COD December 2027
836.5 MW
Capacity
1
Components
Wind
2y 9m
In Queue
IA Executed
IA Status
Signed Apr 2024
Interconnection Timeline
Queue → IA
9 months
IA → COD
3y 8m
Total Duration
9 months
Construction75%
Queue EntryJul 18, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementApr 19, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2027-12-20
Project Details
State
TX
County
Gray
Region
ERCOT
Developer
IP Meitner, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
79000 Gray Substation 345kV
Data Source
LBNL + Live