Lemma Solar
BetaActiveSolarERCOTLBNL + Live
100.61 MW generation in Knox, TX · In queue since April 2023 · Proposed COD July 2028
100.61 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 3m
Facilities Study50%
Queue EntryApr 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
TX
County
Knox
Region
ERCOT
Developer
Greening USA Corp.
Utility
—
Entity
ERCOT
Point of Interconnection
6088 Benjamin AEP 138kV
Data Source
LBNL + Live
No news available for this project.