Western Flats Solar
BetaActiveSolarERCOTLBNL + Live
410.2 MW generation in Crane, TX · In queue since April 2023 · Proposed COD November 2028
410.2 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 7m
Facilities Study50%
Queue EntryApr 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-01
Project Details
State
TX
County
Crane
Region
ERCOT
Developer
Hecate Energy Point Mountain Solar Facility 1 LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 76615 Crane -76635 King Mountain; POI is 7.85 miles from Crane.
Data Source
LBNL + Live
No news available for this project.