Western Flats Solar — Project Summary

Queue ID
ERCOT-26INR0110
Capacity
410.2 MW
Technology
Solar
Status
active
Location
Crane, TX
Region
ERCOT
Developer
Hecate Energy Point Mountain Solar Facility 1 LLC
IA Status
Facility Study

Western Flats Solar

BetaActiveSolarERCOTLBNL + Live

410.2 MW generation in Crane, TX · In queue since April 2023 · Proposed COD November 2028

410.2 MW

Capacity

1

Components

Solar

2y 11m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 7m

Facilities Study50%
Queue EntryApr 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

Project Details

State

TX

County

Crane

Region

ERCOT

Developer

Hecate Energy Point Mountain Solar Facility 1 LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138 kV 76615 Crane -76635 King Mountain; POI is 7.85 miles from Crane.

Data Source

LBNL + Live

No news available for this project.